Mioveni Substation

January this year, EnergoBit signed an important contract which will be developed in 2020 and in the first half of 2021: DDE Design, As Built and execution – Modernization of primary equipment in 110/20kV Mioveni Substation.
The station was commissioned in 1977, having sixteen 110kV cells and two 40MVA transformers:
The works will be developed as follows:
– 110kV substation modernization: replacement of 110kV primary equipment, protection relays upgrade and secondary circuits development, construction works
– 20kV neutral group replacement
The works are complex, but our colleagues are ready to continue to respond with enthusiasm and professionalism in order to successfully complete the project.